Heavy duty filtration at plant October 1st 2007 Eggborough Power Station has
been generating electricity for over
30 years, producing a maximum
output of 2000 Megawatts.A Flue
Gas Desulpherisation plant has
been installed to reduce SO2
emissions and ensure that the
National Air Quality Standards are
met. A new Boll 6.18.2 heavy duty
automatic filter system with 6.18
automatic stand-by filter has been
installed on the FGD water inlet
from the power station water
intake.This removes any
particulates over 100 microns,
preventing the risk of blockages in
the FGD plant."I liked Boll's selfcleaning
technology and the new
heavy duty automatic filter has
proven effective," says Rob
Welborn, FGD Operations."Since
the system has been installed we
have not lost any days of operation
due to water filter blockages." More articles from Bollfilter UK Ltd: |