Register | Login | Set as Home Page | Bookmark | General Enquiries | Help | Thursday, 24th of July 2008
Energy Online Logo Click to visit http://www.encore-int.com/index.php?option=com_wrapper&Itemid=50
Search 
Magazine 
The Latest Energy Prices
Carbon euro 24.70


What next?
 Request further Information    visit web site     Send to friend
 Policy Exchange company's profile
Register for our ENewsletter


Click to visit sponsors web site

Click to visit sponsors web site

Click to visit sponsors web site

Government “missing the boat” on green technology
April 30th 2008

Fitting carbon capture and storage technology could slash global power emissions by 28% by 2050 but timidity and policy incoherence is holding back its large-scale deployment in the UK, according to a new report Is Britain ready for Carbon Capture? by think tank Policy Exchange.

According to the authors of the report, led by Prof.Stuart Haszeldine, confusion over government policy and timescales means that the number of proposed Carbon Capture and Storage (CCS) projects in the UK has halved in the past year.

The 10 projects proposed in 2006/7 would have cut UK base load power emissions by 20% with the first going online in 2009.The loss of the proposed CCS plant at Petershead has deprived the Treasury of £1bn in oil revenues, the authors estimate, as the carbon recovered would have been stored in depleted oil reserves, thereby pushing out more oil.

Tara Singh, one of the report’s authors,explains,“The Government’s timetable for the first CCS plant has slipped from 2009 to 2014. It is a single, small station. As a result, demand in the CCS industry has contracted. Government’s failure to put in place a creative funding package means that the plant will now be built in Abu Dhabi.”

The report examines why Petershead collapsed and questions the capacity for the three new gasfired plants which received approval last year to be built ‘capture ready’ (i.e. able to have the CCS technology strapped on) when the Government has failed to specify what capture, transport and storage facilities would need to be retrofitted.

“The Government is failing to encourage the development of a CCS industry in the UK,”Tara Singh comments. “It is also failing to enable power stations to be ready for CCS once it is developed abroad.

The Government must make it mandatory that any new power plants of a significant size are capture ready.The Government must also set a strong and secure definition for when a capture ready plant must be deploying CCS. “The Government has no clear guidance in place on how carbon should be transported and stored.

Without public engagement and a clear liability regime, carbon from CCS will be seen as the new nuclear waste,and CCS will become as unpopular as nuclear.The Government needs to decide on standards,and then make transparent information available, concerning safety and any possible financial liability.As things stand, policy in this area is a complete mess and the environment and the taxpayer are paying the price.”